Construction@Countway

Newsletter to keep you up to date on all things renovation
 January 18 - January 24
Thank you for subscribing! If this is your first newsletter head to the Countway Renovation webpage for time lapse videos or click on this link to read past issues.

What To Expect INSIDE

  • 1st floor Mechanical, electrical, & plumbing systems investigative work throughout building / investigation above the ceiling on 1st floor
  • New metal stud wall & soffit work on 2nd floor
  • New duct work installation on 2nd floor
  • Plumbing work on 2nd floor
  • Fire Protection work on 2nd floor
  • Drywall work on 2nd floor

What To Expect OUTSIDE

  • No major activities scheduled

Construction Contacts

Question about construction? Issue with noise?

  • Fred Hagerty: fred_hagerty@hms.harvard.edu
  • John Martell: john_martell@hms.harvard.edu
Take a look at our time-lapse video cameras!
Facebook
Twitter
Instagram
Renovation Website
Copyright © 2020 Countway Library, All rights reserved.


Want to change how you receive these emails?
You can update your preferences or unsubscribe from this list.